Subprocess: Project Phase A
Purpose: During Phase A, a project team is formed to fully develop a baseline mission concept and begin or assume responsibility for the development of needed technologies. This work, along with interactions with customers and other potential stakeholders, helps with the baselining of a mission concept and the program requirements on the project. These activities are focused toward System Requirements Review (SRR) and System Definition Review (SDR/PNAR) (or Mission Definition Review (MDR/PNAR)). The SRR and SDR/PNAR (or MDR/PNAR) process culminates in KDP B.
Organization: ORG
Related Links:
Other Views;
Integrated View;
Integrations;
Other Subprocesses;
Process Library;
(Update Library)
Task |
Purpose |
Suggested Roles |
Task Lead(s) |
Estimated Completion Date |
Actual Completion Date |
Documents |
|||||
---|---|---|---|---|---|---|---|---|---|---|---|
Document |
Instructions and Samples |
Document Lead(s) |
Estimated Completion Date |
Actual Completion Date |
Document Location(s) |
||||||
Administration |
The purpose of this task is to provide basic administrative subtasks such as user and document management. |
Phase A Manager,
|
Document Library |
||||||||
Headquarters and Program Products |
The purpose of this task is to provide Headquarters and Program-level products for the Flight Project. |
Phase A Manager, |
Announcement of Opportunity (AOs) |
||||||||
Program Requirements on the Project Plan (Baseline) |
|||||||||||
Acquisition Strategy Meeting (ASM) Minutes (Baseline) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Project Technical Products. |
The purpose of this task is to provide Technical products for the Flight Project. |
Phase A Manager, |
Mission Concept Report (Baseline) |
||||||||
System Level Requirements (Preliminary) |
|||||||||||
Missions Operations Concept (Preliminary) |
|||||||||||
Orbital Debris Assessment (Initial) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Project Planning, Cost, and Schedule Products |
The purpose of this task is to provide Planning, Cost, and Schedule products for the Flight Project. |
Phase A Manager, |
Work Agreement for Next Phase (Baseline) |
||||||||
Integrated Baseline (Preliminary) |
|||||||||||
Project Plan (Preliminary) |
|||||||||||
Cost Analysis Data Requirement (CADRe) (Preliminary) |
|||||||||||
Preliminary Protection Plan (Planetary Protection Certification) |
|||||||||||
Nuclear Safety Launch Approval Plan.(Mission has nuclear materials) (Baseline) |
|||||||||||
Business Case Analysys for Infrastructure (Preliminary) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Key Decision Point (KDP) Readiness Products |
The purpose of this task is to provide Key Decision Point (KDP) Readiness products for the Flight Project. |
Phase A Manager, |
Standing Review Board Report (RB) (Final) |
||||||||
Project Manager Recommendation (includes response to SRB Report, as applicable) (Final) |
|||||||||||
CMC Recommendation (Final) |
|||||||||||
Program Manager Recommendation (Final) |
|||||||||||
MD-PMC Recommendations (for Category I Projects, only) (Final) |
|||||||||||
Governing PMC Recommendation (Final) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
NPR 7120.5D Project Plan-Control Plans |
The purpose of this task is to provide NPR 7120.5D Project Plan-Control Plans products for the Flight Project. |
Phase A Manager, |
Technical, Schedule, and Cost Control Plan (Preliminary) |
||||||||
Safety and Mission Assurance Plan (Preliminary) |
|||||||||||
Risk Management Plan (Preliminary) |
|||||||||||
Acquisition Plan (Preliminary) |
|||||||||||
Technology Development Plan (Baseline) |
|||||||||||
Systems Engineering Management Plan (Baseline) |
|||||||||||
Software Management Plan (Preliminary) |
|||||||||||
Review Plan (Preliminary) |
|||||||||||
Missions Operations Plan (Preliminary) |
|||||||||||
Environment Management Plan (Baseline) |
|||||||||||
Logistics Plan (Preliminary) |
|||||||||||
Science Data Management Plan (Preliminary) |
|||||||||||
Information and Configuration Management Plan (Preliminary) |
|||||||||||
Security Plan (Preliminary) |
|||||||||||
Export Control Plan (Preliminary) |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Review Packages |
The purpose of this task is to provide Review Packages products for the Flight Project. |
Phase A Manager, |
Key Decision Point (KDP) B Package |
||||||||
Acquisition Strategy Planning Meeting (ASPM) Package |
|||||||||||
Systems Requirements Review (SRR) Package |
|||||||||||
Systems Defintion Review (SDR) Package |
|||||||||||
Preliminary Non-Advocate Review (PNAR) Package |
|||||||||||
Mission Definition Review (MDR) Package |
|||||||||||
Peer Review (MCR) Package |
|||||||||||
Subsystem Preliminary Design Review (PDR) Package |
|||||||||||
Subsystem Critical Design Review (CDR) Package |
|||||||||||
System Review (SR) Package |
|||||||||||
Reviews |
|||||||||||
Approvals |
|||||||||||
Analysis |
The purpose of this task is to generate reports from the data resulting from the subprocess. |
Phase A Manager, |
Administration Reports |
||||||||
Headquarters and Program Reports |
|||||||||||
Project Technical Reports |
|||||||||||
Project Planning, Cost, and Schedule Reports |
|||||||||||
Key Decision Point (KDP) Readiness Reports |
|||||||||||
NPR 7120.5D Project Plan-Control Plans Reports |
|||||||||||
Review Packages Reports |
|||||||||||
Reviews |
|||||||||||
Approvals |